02 — CASE STUDY
How the work came together
01
Challenge
The plant’s main packaging line was 12 years old and running well below its rated speed. Changeovers took most of a shift, and the client could not afford a long shutdown during peak season.
02
Solution
We split the retrofit into four short phases, each fitted into a planned weekend stop. New servo drives, a vision reject system and a rebuilt HMI went in while the line kept producing between phases.
03
Result
Throughput rose by more than a third and changeovers now take under an hour. The line never lost a production week, and operators were trained on each phase before it went live.